MINING & EXPLORATION PROJECTS

Philippines

CO-O OPERATIONS

1.1   The Co-O Mine

The Co-O underground mine is developed on a series of intermediate sulphidation, epithermal quartz veins and to date have been worked to approximately 370 metres below the highest point. When the mine was originally developed in the late 1980s, the vein system had only been discovered on the west side of the Oriental Fault (despite exploration drilling on the east side) and all mine development was carried out on the west side over approximately 600 metres of strike length. The mine is accessed through an adit for nearly 300 metres before encountering the mineralised veins. The height above sea level of the adit is 150 metres but for convenience this is now designated as Level I (previously 3150 metre level).

The current bottom of the Mine at Level 6 is 250 metres below adit or Level 1.  The sixth level at 250 metres depth was commenced in the September 2010 quarter.

The Co-O Mine vein system trends westerly and is truncated by a major north-trending fault (the Oriental Fault) which has vertically downthrown the vein system on the eastern side of the fault by an estimated 300 metres and moved the veins horizontally by approximately 20 to 40 metres, with the east side moved to the south. The effect of the downthrow is that the Co-O veins on the east side of the fault are not exposed at surface and the tops of most veins commence approximately 160 metres below surface and below Level I. 

Drilling, which commenced in late 2004, intersected the vein system on the east side of the Oriental Fault and subsequently has delineated the vein system over a strike length of approximately 850 metres to east of the Oriental Fault. Drilling to the west has extended the veins giving a total strike length of approximately 1,600 metres.

Additional geological information is available in the announcement dated 24 August 2011.

It is important to note that drilling of narrow epithermal veins at best generally provides only an indication of the presence of the gold mineralised vein and rarely provides good quantitative data with respect to accurate grade and volume estimations for some or all of the following reasons:

  • Veins commonly pinch and swell and may be brecciated or displaced by faults;

  • Gold distribution is commonly erratic, in shoots or controlled by structures within the vein; and

  • Drill core recovery can be reduced because of the brecciation and soft unconsolidated material and hence the recovered material may not be representative of the material drilled.

Consequently, the Company regards the initial drilling as indicative only and operates the policy of using drilling to locate the extent of the mineralised veins. This is then followed by level development to support the drilling results, to provide a more accurate estimate of vein grades and to facilitate the estimation of resources and conversion of Indicated Resources to Probable Reserves.

See the section on Narrow Vein Mining for more information.
 

1.2   Gold Production

The production statistics are summarised in Table 1.

Table 1. Gold production statistics for financial years ended 30 June 2010 and 2011

Period Unit Year ended 
30 June 2011
Year ended 
30 June 2010
Tonnes mined wet tonnes 262,610 198,693
Ore milled dry tonnes 266,613 179,609
Recovered grade gpt 12.63 16.52
Recovery % 94% 94%
Gold produced ounces 101,474 89,679
Cash costs US$ $189 $184
Gold sold ounces 96,217 64,020
Average gold price received US$ $1,371 $1,100

Note:
(1) Net of development costs and includes royalties and local business taxes but no by-product credits

The Co-O Mine produced a record 101,474 ounces of gold for the year, an increase of 11,795 ounces or 13% above the previous year's production of 89,679 ounces, at a recovered grade of 12.63 g/t gold (2009: 16.52 g/t gold) and cash costs of US$189 per ounce (2010: US$184 per ounce).

The production guidance for the forthcoming financial year is between 100,000 to 110,000 ounces at cash costs of circa US$200 per ounce (inclusive of royalties and local business taxes and no by-product credits).

A breakdown of actual and forecasted production ounces and cost per ounce by quarters for the last four quarters of this fiscal year is highlighted in Graph 1.

1.3   Resources and Reserves

In July 2011 the Company completed resource estimations for the Co-O Mine based on drilling and underground development.  In August 2010 a new reserve estimate was published.  The estimations are based on 3D mine frame models of the veins.  The Resource estimation has maintained the Indicated Resources and has increased Inferred ounces by 238,000 ounces to 898,000 ounces using a lower cut of 0 g/t gold.

Table 3: Global Resources

Category  tonnes g/t gold ounces
Indicated 1,601,000 12.0 616,000
Inferred 4,747,000 8.8 1,344,000
Total 6,348,000 9.6 1,960,000
Notes: 
- A lower cut-off of 0 g/t gold has been applied;
- Various upper cuts have been applied; and
- Resources are inclusive of reserves.

Resource estimations were undertaken by Cube Consulting Pty Ltd of Perth, Western Australia.

Table 4: Reserve Estimations

Category  tonnes g/t gold ounces
Probable reserves 1,500,000 10.1 502,000
Notes:
- Reserves based on a a US$1,000 per ounce gold price 
  and a stope cut-off grade of 3.0 g/t gold; and
- Reserves are included in the resource estimate.

The reserve estimations were undertaken by Carras Mining Pty Ltd of Perth, Western Australia.

Composite Level Plan of Co-O
Figure 1
. Composite level plan of Co-O Level 6.
View Enlargement


Figure 2.
 3D model of the Co-O vein system.
View Enlargement 


Photograph of the Saga Shaft temporary headframe.  View Enlargement


1.4   Co-O Mine

(a) Mine 

The Mine has produced 101,474 ounces for the year ended 30 June 2011.  Forecast production for FY 2011/12 is 100-110,000 ounces.

(b) Mill

The new leach tanks and thickener have been completed, and the gold room expansion completed.

(c) Tailings Dam

Construction of a new eight year life tailings dam was completed.

(d)  Power

A dedicated power line to the Company's operations was completed on schedule in late November 2010.


Figure 3
. Composite longitudinal projection of the Co-O Mine and drill hole intersections.
View Enlargement.

Figure 4
. Regional map of the Co-O Mine and adjacent veins.
View Enlargement
** The potential target size and grade is conceptual in nature, and there has been insufficient exploration to define a mineral resource, and it is uncertain if further exploration will result in the target being defined as a mineral resource. Refer to Stock Exchange announcement dated 24 August 2011.

Tenement location map showing the gold mines and prospects.  View enlargement

1.5  Co-O Mine Conceptual Target Size

Estimates (Table 2) have been undertaken for the Co-O Mine conceptual target size** based on a drill-defined strike length of approximately 1,600 metres and up to 2,000 metres based on potential extensions.

The range for the Conceptual Exploration Target remains well supported at 3,000,000 ounces in 9,800,000 tonnes to 7,000,000 ounces in 23,500,000 tonnes using a grade range of 9 to 11 g/t gold with a preferred average grade of 10 g/t gold as shown in Table 2.

The additional support for this target is listed below:

  • The total ounces already accounted by the current global resource and past production is approximately 2,310,000 ounces.

  • An increase of 100 metres of strike length from 1,500 metres to 1,600 metres as supported by drilling as described in the announcement dated 6 July 2011.

  • A change in the Specific Gravity ("SG") to the SG currently used of 2.62 for the resource estimates (previously 2.45) resulting in a 7% increase in tonnes as reported in the announcement dated 22 July 2010; and

  • As shown on the composite longitudinal projection in Figure 3, all new drill holes since 30 June 2011 in the deposit with assays of 0.2 metres at 3 g/t gold up to 30 June 2011 are incorporated and support the mineralisation continuing to depth. The assays support levels between 500 metres and 750 metres below surface is a function of the amount of drilling completed to date.

View Table 2 here.


1.6  New Co-O Plant

The Board on 17 November 2010 approved construction of a new Co-O plant with capacity to produce 200,00 ounces per year.

Capital requirements of the new plant (inclusive of mine development) have been reduced from US$80 million to US$70 million and will be funded out of cashflow.

The construction schedule after regulatory permitting is estimated to be approximately 18 months.

 © Medusa Mining Limited.   Legal Notice  |  Contact us